PROJECTS
Regina Bypass Project Agreement
The Saskatchewan Government is moving forward with the Regina Bypass as a design-build-finance-operate-maintain public-private partnership (P3) procurement model. Construction on the new Regina Bypass began in summer 2015 and will be complete by fall 2019.- Schedule 1 - Appendix 1 - Ministry Permits Licences and Approvals
- Schedule 1 - Definitions and Interpretation
- Schedule 2 - Completion Documents
- Schedule 3 - Custody Agreement
- Schedule 4 - Lenders' Direct Agreement
- Schedule 5 - Construction Contractor's Direct Agreement
- Schedule 6 - Independent Certifier Agreement
- Schedule 7 - Project Co Information
- Schedule 8 - Key Individuals
- Schedule 9 - Review Procedure
- Schedule 10 - Works Report Requirements
- Schedule 11 - Proposal Extracts
- Schedule 12 - Communications Protocol
- Schedule 13 - Record Provisions
- Schedule 14 - Integrated Management System
- Schedule 15-1 - 100 - General
- Schedule 15-2 - 200 - Design
- Schedule 15-2 - 300 - Construction
- Schedule 15-2 - Appendix A - Concept Drawings
- Schedule 15-2 - Appendix B - Concrete Surface Finishing Details
- Schedule 15-2 - Appendix C - Add Resources
- Schedule 15-2 - Appendix D - Guide Signing
- Schedule 15-2 - Appendix E - Phase One Drawing
- Schedule 15-2 - Appendix F - ITS Requirements
- Schedule 15-2 - Appendix G - Traffic Modeling and Traffic Signal Guidelines
- Schedule 15-2 - Appendix H - Right of Way Drawings
- Schedule 15-2 -Appendix I - Global Memoranda of Understanding
- Schedule 15-2 -Appendix J - Clar Sketches
- Schedule 15-3 - 400 - Overview
- Schedule 15-3 - 401 - Operations and Maintenance
- Schedule 15-3 - 402 - Asset Preservation
- Schedule 15-3 - 500 - Handback Requirements
- Schedule 15-3 - Appendix A - OMR Limits
- Schedule 15-3 - Appendix B - Snow Plowing Limits
- Schedule 15-3 - Appendix C - WRB Interim Maintenance Section
- Schedule 16 - Commissioning
- Schedule 18 - Payment Mechanism
- Schedule 19 - Variation Procedure
- Schedule 20 - Compensation on Termination
- Schedule 21 - Handback Procedure
- Schedule 22 - Dispute Resolution Procedure
- Schedule 23 - INTENTIONALLY DELETED
- Schedule 24 - Insurance Requirements
- Schedule 25 - Insurance Trust Agreement
- Schedule 26 - Refinancing
- Schedule 27 - Standby Letter of Credit
- Schedule 28 - OM Interim Services Agreement
- Schedule 29 - Additional Works and Third Party Works
- Schedule 30 - Construction Period Performance